PROJECT: Supernatent Tank Roof Removal

Client: Magnox

Location: Hunterston, West Kilbride, Ayrshire

Project Length: 3 months

Project Overview

BD Nuclear were commissioned to remove the roof from three concrete sludge tanks under C3 Conditions.  The work required the roofs to be removed in small sections due to lifting constraints.  To ensure the lifting operations were undertaken as safely as possible our bespoke harpoons were utilised. 
 
The work was undertaken using a stich drilling technique and was completed without issue within the agreed programme timeframe.

<< VIEW ALL PROJECT PHOTOS >>